Parameters and Quotation of 15 Tons Per Hour Coal Fired Steam Boiler in Pakistan

2022-01-04

 We are a part of leading Petrochemicals Group which has been at the forefront of the global petrochemicals business in Pakistan. Our Group has consistently expanded and we have invested in state-of-the-art production facilities, distribution networks, storage capacities and human talent.

We are now setting up a Chemical Plant in Pakistan (near Faisalabad City), for which we require Coal Fired Boiler at our Plant, PFA for the Coal fired Boiler in attachment and quote your Lowest Possible rates ASAP.

Coal Fired Steam Boiler

Coal Fired Steam Boiler

RFQ for Coal Fired Boiler

Description Units  Parameters Details
Rated Capacity  Ton/hr 15
Steam pressure main steam stop valve bara 31
Steam temperature °C 232
Deaerator temperature °C 105
Condensate return flow % 85
Normal Feed water temperature  °C 105
Demin water temperature ⁰C 26
Fuel   Coal , Biomass Rice husk etc.
Efficiency % 85
Heating Area  542
Combustion system and Recycle system  Vendors Should include all conventional parts of Coal fired oil heater
Electrical and Control system   Conventional PLC control panel and associated power panel. Vendors describes the details 
Instrument and Mechanical Parts    System should include all necessary instruments for plant monitoring and safety. Mainly described by Vendors
Fuel    Coal , Biomass Rice husk etc.
Dimensions LXWXH 9300X 3300 X3500
Steam Distributor   DN500
Weight of Boiler Tons 52

Scope of Work/supply

1.1 VENDOR shall be responsible for the complete design, supply of materials, prefabrication, shop assembling, shop inspection, tests, guarantee, painting, packing, transportation, testing & commissioning of the entire boiler packages.

& commissioning of the entire boiler packages.

1.2 The offer shall include the supply of complete package including all equipment, piping, instrumentation & electrical works, skid structure, valves, pumps platforms, automatic combustion control system, ignition control system, flame detection and ESD system except concrete design and or any civil construction work.

1.3 VENDOR shall also list the spare parts for commissioning as well as for two-year operation and maintenance.

1.4 The vendor’s quotation should include the design/supply of coal handling system

1.5 Vendor shall design the system with proper equipment protection in regard to HSE, operability and maintainability. In addition, implementation of the best practices for the the system and Equipments are also required to be considered by Vendor. The system or part of system/equipment shall be able to isolate such that for safe maintenance activities.

1.6 Utilities consumption summary for the Steam Boiler packages to be also submitted with the Vendor’s offer.

1.7 Analyzers, Fire & Gas detection system, interface to DCS, PLC, as applicable for steam Boiler package should be included in the scope of Vendor.

1.8 Vendor scope of supply shall also include all instruments indications, alarms, controls & interlock for the boiler package unit which will be implemented in new DCS/PLC systems and tie-in with PA-Chem facility

1.9 Vendor has to comply with the hazardous area classification

 

1.10 Vendor to provide on-site support for the pre-commissioning and of commissioning the whole unit until stable operation is achieved.

Parameters, Quotation,15 Tons Per Hour, Coal Fired Steam Boiler, Pakistan

Get An Instant Quotation

For all inquiries, please fill in the form below (* are required) to send us a brief message, and we will get back to you as soon as possible.


  • Heat Converters
  • Pressure Converters
  • Temperature Converters

Any question, please contact us for free. Phone number: +86-371-86686767 Skype: zgboiler Email:zbgboiler@zzboiler.com

KW
bar
    °C