WNS2.1-1.0-95/70-YQ 3 tons of gas heating boiler host and auxiliary equipment list configuration

2023-06-29

 WNS2.1-1.0-95/70-YQ 3 tons of gas heating boiler host and auxiliary equipment list configuration

item number item name Specifications quantity unit   Arrival date (as defined by the International Chamber of Commerce Incoterms)
Earliest Arrival Date latest arrival date Bidder's arrival date [to be filled in by the bidder]
one, The main material of the process part            
1 Gas hot water boiler Power 2.1MW, equipment pressure 1.0 MPa, supply and return water temperature 95/70℃, including burner, NOx<30mg/m3 2 tower 30 days after signing the contract 45 days after signing the contract  
1-1 Flue gas condenser Supporting 2.1MW boiler 2 tower 30 days after signing the contract 45 days after signing the contract  
1-2 2.1MW boiler supporting sound insulation cover Supporting 2.1MW boiler 2 set 30 days after signing the contract 45 days after signing the contract  
2 primary circulation pump Q=340m3/h, H=32mH2O P=55kW, frequency conversion 2 tower 30 days after signing the contract 45 days after signing the contract  
3 primary water pump Q=7m3/h, H=34mH2O P=1.5kW, frequency conversion 2 tower 30 days after signing the contract 45 days after signing the contract  
4 Automatic water softener Softened water volume 12m3/h 1 set 30 days after signing the contract 45 days after signing the contract  
5 soft water tank V=8m3, 2.0m×2.0m×2.0m 1 tower 30 days after signing the contract 45 days after signing the contract  
6 Vertical decontamination device DN250 PN10, straight-through 1 tower 30 days after signing the contract 45 days after signing the contract  
two, Main materials of hot water system            
1 Y type decontamination device DN65PN10 1 indivual 30 days after signing the contract 45 days after signing the contract  
2 butterfly valve DN250 PN16 D341H-16 9 indivual 30 days after signing the contract 45 days after signing the contract  
    DN150 PN16 D341H-16 4 indivual 30 days after signing the contract 45 days after signing the contract  
3 Flange check valve DN250 PN16 H44H-16C 3 indivual 30 days after signing the contract 45 days after signing the contract  
    DN65 PN16 H44H-16C 3 indivual 30 days after signing the contract 45 days after signing the contract  
    DN40 PN16 H44H-16C 2 indivual 30 days after signing the contract 45 days after signing the contract  
4 Manual control valve DN200 PN16 H40H-16 2 indivual 30 days after signing the contract 45 days after signing the contract  
5 Flange globe valve DN200 PN16 J41H-16C 2 indivual 30 days after signing the contract 45 days after signing the contract  
    DN65 PN16 J41H-16C 11 indivual 30 days after signing the contract 45 days after signing the contract  
    DN32 PN16 J41H-16C 3 indivual 30 days after signing the contract 45 days after signing the contract  
6 Flange metal soft joint DN250PN10 4 indivual 30 days after signing the contract 45 days after signing the contract  
    DN65PN10 4 indivual 30 days after signing the contract 45 days after signing the contract  
7 Spring micro-open safety valve DN32 A47H-16C 1 indivual 30 days after signing the contract 45 days after signing the contract  
8 head size DN250/DN200 6 indivual 30 days after signing the contract 45 days after signing the contract  
    DN65/DN50 4 indivual 30 days after signing the contract 45 days after signing the contract  
9 backflow preventer DN65 1 indivual 30 days after signing the contract 45 days after signing the contract  
10 cold water meter DN65 2 indivual 30 days after signing the contract 45 days after signing the contract  
11 Industrial Bimetallic Thermometer 0-100°C 4 indivual 30 days after signing the contract 45 days after signing the contract  
12 Spring Tube Pressure Gauge 0-1.0MPa 13 indivual 30 days after signing the contract 45 days after signing the contract  
13 seamless steel pipe ∅273×7 160 rice 30 days after signing the contract 45 days after signing the contract  
    ∅219×6 80 rice 30 days after signing the contract 45 days after signing the contract  
    ∅159×4.5 30 rice 30 days after signing the contract 45 days after signing the contract  
    ∅108×4 40 rice 30 days after signing the contract 45 days after signing the contract  
    ∅76×3.5 100 rice 30 days after signing the contract 45 days after signing the contract  
    ∅45×2.5 30 rice 30 days after signing the contract 45 days after signing the contract  
    ∅38×2.5 40 rice 30 days after signing the contract 45 days after signing the contract  
14 Steel for hangers   180 kg 30 days after signing the contract 45 days after signing the contract  
15 Aluminum silicate   8 m3 30 days after signing the contract 45 days after signing the contract  
16 0.5mm galvanized iron sheet   200 m2 30 days after signing the contract 45 days after signing the contract  
17 Exhaust valve DN20PN16 10 indivual 30 days after signing the contract 45 days after signing the contract  
18 floor drain DN100 3 indivual 30 days after signing the contract 45 days after signing the contract  
19 Ductile Iron Pipe DN100 20 rice 30 days after signing the contract 45 days after signing the contract  
  Process piping installation supporting services            
1 Valve insulation 1. Insulation material: aluminum silicate
2. Insulation thickness: see design instructions for details
3. Valve specifications: see design drawings for details
0.5 m3 Complete within 10 days after arrival Completed within 30 days of arrival  
2 Flange insulation 1. Insulation material: aluminum silicate
2. Insulation thickness: see design instructions for details
3. Flange specifications: see design drawings for details
0.5 m3 Complete within 10 days after arrival Completed within 30 days of arrival  
3 Weld X-ray inspection 1. Name: X-ray flaw detection of weld seam
2. Film specification: 80mm*300mm
3. Tube wall thickness: within 16
50 open Complete within 10 days after arrival Completed within 30 days of arrival  
4 Pipeline corrosion protection 1. Rust removal level: St3 very thorough manual and power tool rust removal
2. Brushing (spraying) type: Hongdan epoxy anti-rust paint
3. Brushing (spraying) times, paint film thickness: two times
180 m Complete within 10 days after arrival Completed within 30 days of arrival  
5 Corrosion protection for general steel structures 1. Rust removal level: St3 very thorough manual and power tools
2. Brushing (spraying) variety: Hongdan epoxy anti-rust paint
3. Number of brushing (spraying) times, paint film thickness: see design instructions for details
100 kg Complete within 10 days after arrival Completed within 30 days of arrival  
three, The main material of the flue gas system            
1 Double-layer insulation stainless steel chimney DN400, height 20m 2 seat 30 days after signing the contract 45 days after signing the contract  
2 round flue Inner diameter ∅400 δ=5mm 4 m 30 days after signing the contract 45 days after signing the contract  
3 90 elbow DN400 R=450mm δ=5mm 2 indivual 30 days after signing the contract 45 days after signing the contract  
4 chimney muffler DN400 2 tower 30 days after signing the contract 45 days after signing the contract  
5 Accident exhaust fan in boiler room Low-noise DFBP35-11-6.3# explosion-proof axial flow fan, single air volume 9585m3/h 2 tower 30 days after signing the contract 45 days after signing the contract  
6 Inlet muffler for boiler room Size 800×630, single air volume 7000m3/h 2 tower 30 days after signing the contract 45 days after signing the contract  
Four heating system            
1 Steel round two-column radiator GZY2-1.0/6-1.0 18 pieces 10 Group 30 days after signing the contract 45 days after signing the contract  
2 Galvanized steel DN40 20 rice 30 days after signing the contract 45 days after signing the contract  
    DN32 100 rice 30 days after signing the contract 45 days after signing the contract  
    DN20 80 rice 30 days after signing the contract 45 days after signing the contract  
3 ball valve Q11T-16 DN15 20 indivual 30 days after signing the contract 45 days after signing the contract  
4 Shut-off valve J11T-16 DN40 2 indivual 30 days after signing the contract 45 days after signing the contract  
5 Auto exhaust valve ZP-II DN32 4 indivual 30 days after signing the contract 45 days after signing the contract  
  Heating pipe installation supporting services            
1 Pipe oiling 1. Rust removal level: St2 Thorough manual and power tool rust removal
2. Paint type: anti-rust paint
3. Number of times of brushing, paint film thickness: see design instructions for details
200 m Complete within 10 days after arrival Completed within 30 days of arrival  
WNS2.1-1.0-95/70-YQ, 3 tons,gas heating boiler,equipment list configuration

Get An Instant Quotation

For all inquiries, please fill in the form below (* are required) to send us a brief message, and we will get back to you as soon as possible.


  • Heat Converters
  • Pressure Converters
  • Temperature Converters

Any question, please contact us for free. Phone number: +86-371-86686767 Skype: zgboiler Email:zbgboiler@zzboiler.com

KW
bar
    °C