WNS2.8-1.0-95/70-YQ gas boiler host and auxiliary equipment list configuration
2023-06-25
WNS2.8-1.0-95/70-YQ gas boiler host and auxiliary equipment list configuration
item number | item name | Specifications | quantity | unit | Arrival date (as defined by the International Chamber of Commerce Incoterms) | ||
Earliest Arrival Date | latest arrival date | Bidder's arrival date [to be filled in by the bidder] | |||||
one, | The main material of the process part | ||||||
1 | Gas hot water boiler | Power 2.8MW, equipment pressure 1.0 MPa, supply and return water temperature 95/70℃, including burner, NOx<30mg/m3 | 2 | tower | 30 days after signing the contract | 45 days after signing the contract | |
1-1 | Flue gas condenser | Supporting 2.8MW boiler | 2 | tower | 30 days after signing the contract | 45 days after signing the contract | |
1-2 | 2.8MW boiler supporting sound insulation cover | Supporting 2.8MW boiler | 2 | set | 30 days after signing the contract | 45 days after signing the contract | |
2 | primary circulation pump | Q=300m3/h, H=28mH2O P=45kW, frequency conversion | 2 | tower | 30 days after signing the contract | 45 days after signing the contract | |
3 | primary water pump | Q=3m3/h, H=28mH2O P=0.55kW, frequency conversion | 2 | tower | 30 days after signing the contract | 45 days after signing the contract | |
4 | Automatic water softener | Softened water volume 12m3/h | 1 | set | 30 days after signing the contract | 45 days after signing the contract | |
5 | soft water tank | V=10m3, 2.5m×2.0m×2.0m | 1 | tower | 30 days after signing the contract | 45 days after signing the contract | |
6 | Vertical decontamination device | DN250 PN10, straight-through | 2 | tower | 30 days after signing the contract | 45 days after signing the contract | |
7 | Heat exchange unit | Total heat exchange 5.5MW | 1 | set | 30 days after signing the contract | 45 days after signing the contract | |
7-1 | Plate heat exchanger | The heat exchange capacity of a single unit is 3.85MW, the pressure of the equipment is 1.0MPa, and a single unit bears 70% of the heat load | 2 | tower | 30 days after signing the contract | 45 days after signing the contract | |
7-2 | Circulating water pump for heat exchange system | Q=300m3/h, H=34mH2O P=45kW, frequency conversion | 2 | tower | 30 days after signing the contract | 45 days after signing the contract | |
7-3 | Make-up water pump for heat exchange system | Q=11m3/h, H=36mH2O P=2.2kW, frequency conversion | 2 | tower | 30 days after signing the contract | 45 days after signing the contract | |
two, | Main materials of hot water system | ||||||
1 | Y type decontamination device | DN65PN10 | 1 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
2 | butterfly valve | DN250 PN16 D341H-16 | 11 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
DN100 PN16 D341H-16 | 6 | indivual | 30 days after signing the contract | 45 days after signing the contract | |||
3 | Flange check valve | DN250 PN16 H44H-16C | 2 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
DN200 PN16 H44H-16C | 1 | indivual | 30 days after signing the contract | 45 days after signing the contract | |||
DN50 PN16 H44H-16C | 2 | indivual | 30 days after signing the contract | 45 days after signing the contract | |||
DN40 PN16 H44H-16C | 3 | indivual | 30 days after signing the contract | 45 days after signing the contract | |||
4 | Manual control valve | DN150 PN16 H40H-16 | 3 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
5 | Flange globe valve | DN150 PN16 J41H-16C | 2 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
DN100 PN16 J41H-16C | 1 | indivual | 30 days after signing the contract | 45 days after signing the contract | |||
DN65 PN16 J41H-16C | 6 | indivual | 30 days after signing the contract | 45 days after signing the contract | |||
DN50 PN16 J41H-16C | 6 | indivual | 30 days after signing the contract | 45 days after signing the contract | |||
DN40 PN16 J41H-16C | 3 | indivual | 30 days after signing the contract | 45 days after signing the contract | |||
DN32 PN16 J41H-16C | 2 | indivual | 30 days after signing the contract | 45 days after signing the contract | |||
6 | Flange metal soft joint | DN250PN10 | 4 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
DN50PN10 | 4 | indivual | 30 days after signing the contract | 45 days after signing the contract | |||
7 | Spring micro-open safety valve | DN32 A47H-16C | 1 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
8 | head size | DN250/DN200 | 6 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
DN50/DN40 | 4 | indivual | 30 days after signing the contract | 45 days after signing the contract | |||
9 | backflow preventer | DN65 | 1 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
10 | cold water meter | DN65 | 2 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
DN50 | 1 | indivual | 30 days after signing the contract | 45 days after signing the contract | |||
11 | Industrial Bimetallic Thermometer | 0-100°C | 6 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
12 | Spring Tube Pressure Gauge | 0-1.0MPa | 17 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
13 | seamless steel pipe | ∅273x7 | 170 | rice | 30 days after signing the contract | 45 days after signing the contract | |
∅219×6 | 15 | rice | 30 days after signing the contract | 45 days after signing the contract | |||
∅159×4.5 | 60 | rice | 30 days after signing the contract | 45 days after signing the contract | |||
∅108×4 | 70 | rice | 30 days after signing the contract | 45 days after signing the contract | |||
∅76×3.5 | 35 | rice | 30 days after signing the contract | 45 days after signing the contract | |||
∅57×3.5 | 20 | rice | 30 days after signing the contract | 45 days after signing the contract | |||
∅45X2.5 | 30 | rice | 30 days after signing the contract | 45 days after signing the contract | |||
∅38X2.5 | 30 | rice | 30 days after signing the contract | 45 days after signing the contract | |||
14 | Steel for hangers | 180 | kg | 30 days after signing the contract | 45 days after signing the contract | ||
15 | Aluminum silicate | 7 | m3 | 30 days after signing the contract | 45 days after signing the contract | ||
16 | 0.5mm galvanized iron sheet | 180 | m2 | 30 days after signing the contract | 45 days after signing the contract | ||
17 | Exhaust valve | DN20PN16 | 10 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
18 | floor drain | DN100 | 3 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
19 | Ductile Iron Pipe | DN100 | 20 | rice | 30 days after signing the contract | 45 days after signing the contract | |
Process piping installation supporting services | |||||||
1 | Valve insulation | 1. Insulation material: aluminum silicate 2. Insulation thickness: see design instructions for details 3. Valve specifications: see design drawings for details |
1 | m3 | Complete within 10 days after arrival | Completed within 30 days of arrival | |
2 | Flange insulation | 1. Insulation material: aluminum silicate 2. Insulation thickness: see design instructions for details 3. Flange specifications: see design drawings for details |
1 | m3 | Complete within 10 days after arrival | Completed within 30 days of arrival | |
3 | Weld X-ray inspection | 1. Name: X-ray flaw detection of weld seam 2. Film specification: 80mm*300mm 3. Tube wall thickness: within 16 |
100 | open | Complete within 10 days after arrival | Completed within 30 days of arrival | |
4 | Pipeline corrosion protection | 1. Rust removal level: St3 very thorough manual and power tool rust removal 2. Brushing (spraying) type: Hongdan epoxy anti-rust paint 3. Brushing (spraying) times, paint film thickness: two times |
260 | m | Complete within 10 days after arrival | Completed within 30 days of arrival | |
5 | Corrosion protection for general steel structures | 1. Rust removal level: St3 very thorough manual and power tools 2. Brushing (spraying) variety: Hongdan epoxy anti-rust paint 3. Number of brushing (spraying) times, paint film thickness: see design instructions for details |
180 | kg | Complete within 10 days after arrival | Completed within 30 days of arrival | |
three, | The main material of the flue gas system | ||||||
1 | Double-layer insulation stainless steel chimney | DN500, height 20m | 2 | seat | 30 days after signing the contract | 45 days after signing the contract | |
2 | round flue | Inner diameter ∅500 δ=5mm | 4 | m | 30 days after signing the contract | 45 days after signing the contract | |
3 | 90 elbow | DN500 R=550mm δ=5mm | 2 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
4 | chimney muffler | DN500 | 2 | tower | 30 days after signing the contract | 45 days after signing the contract | |
5 | Accident exhaust fan in boiler room | Low-noise DFBP35-11-5.6# explosion-proof axial flow fan, single air volume 5361m3/h | 3 | tower | 30 days after signing the contract | 45 days after signing the contract | |
6 | Inlet muffler for boiler room | The size is 800×500, and the maximum air volume of a single unit is 5500m3/h | 3 | tower | 30 days after signing the contract | 45 days after signing the contract | |
Four | heating system | ||||||
1 | Steel round two-column radiator | GZY2-1.0/6-1.0 18 pieces | 16 | Group | 30 days after signing the contract | 45 days after signing the contract | |
2 | Galvanized steel | DN40 | 80 | rice | 30 days after signing the contract | 45 days after signing the contract | |
DN32 | 80 | rice | 30 days after signing the contract | 45 days after signing the contract | |||
DN20 | 80 | rice | 30 days after signing the contract | 45 days after signing the contract | |||
3 | ball valve | Q11T-16 DN15 | 32 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
4 | Shut-off valve | J11T-16 DN40 | 2 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
5 | Auto exhaust valve | ZP-II DN32 | 6 | indivual | 30 days after signing the contract | 45 days after signing the contract | |
Heating pipe installation supporting services | |||||||
1 | Pipe oiling | 1. Rust removal level: St2 Thorough manual and power tool rust removal 2. Paint type: anti-rust paint 3. Number of times of brushing, paint film thickness: see design instructions for details |
240 | m | Complete within 10 days after arrival | Completed within 30 days of arrival |
WNS2.8-1.0-95/70-YQ, gas boiler host ,auxiliary equipment list configuration