Project Scope of Boiler
2022-07-18
PROJECT SCOPE
- Boiler (burning + furnace system + steam caisson)
- Garner Feeder
- Pre-heated air
- Primary Air Fan
- Secondary Air Fan
- Exhaust I
- nterconnection Pipeline (Air and Gases)
- Chimney Freestanding
- Inspection Covers
- Soot blower
- Ashes Extraction System
- Water Feed Pumps
- Safety Valves
- Fund Discharge
- Refractory Concrete
- Thermal Insulation and Coating
- Platforms & Stairs
- Painting
- Electric Panel - CCM
- Eletric Motors
- Level Bottle
- Level Indicator
- Level control of 3 elements S
- Supervision and Control System
- gauge
- Saver
- Salts Continuous Discharge
- Superheater
- Desuperheater
- Multicyclone Filter
- Gas Analyzer
- Deaerator
- Condensate
- Discharge Tank Background
- Damper
- Eletrical Interconnection Material
- Main Steam Lines
- Discharge lines of safety valves
- Feed Water Lines and Condensate Return
- Compressed Air Lines
- Superheated Steam pipe
- Turbine - 2.5 MW
- Eletric Generator
- Condenser
- Cooling Tower
- Water Cooling Pumps
- General Power Board
- General Automation Board
- General Transformer Board
- General Generator Board
- General Cooling System Board
- General Auxiliary Circuits Board
- Interconnection Materials
- Construction Structure (by our client)
- Assemblers Travel Expenses (by our client)
SERVICES
- Coordinator for Mechanical Assembly
- Tools and Inputs for Mechanical Assembly
- Helpers for Mechanical Assembly
- Engineer/Coordinator for Electric Assembly
- Tools and Inputs for Electrical Installation
- Helpers for Electrical Mounting
- Eletrical Interconnection Assembly
- Hosting, Food &Transportation for the Professionals
- Cranes for Equipment Discharges and Assembly
- Refractory Concrete Labour
- Structure Works Equipment (by our client)
Boiler